Rehabilitation & Reconstruction of Park, Mall & Servitude Rd: Phase 2

Major upgrades on Mall and Park Road will impact on road users for the next few weeks until Easter 2019.

DESCRIPTION:

Rehabilitation of Mall Road from Knysna Road to Builders Warehouse, and the rehabilitation of a section of Park Road near the Blue Mountain Circle. 

PROJECT PERIOD:

 14th March to 18th April 2019.

SERVICE DISRUPTION

No municipal service disruption is anticipated as a direct result of the works. Water, electricity and sanitation service should not be affected by the project.

TRAFFIC IMPACT:

During construction access to the Garden Route Mall, Eden Meander, SARS and Blue Mountain will be maintained at all times.  The work on Mall Road is expected to cause some delays at peak periods due to high traffic volumes.

Extra care is to be taken by road users throughout the duration of the entire construction period. Adherence to temporary road signs and markings will be required.

The safety and convenience of travelling public are of utmost importance. Every effort will be made to ensure that there is minimal disruption during construction and that due courtesy is extended to the travelling public.

PROJECT ENQUIRIES: (to be confirmed)

The George Municipality apologises for the inconvenience and appeals to road users to be patient and exercise caution near roadworks.

Please look out for and adhere to special road signage and roadworks personnel.

Details of more roadworks projects to follow shortly.